Woolwich Arsenal extension wins award
13-11-2009
13-11-2009
The new DLR Extension at Woolwich Arsenal comprises 2.5k of new railway in parallel twin bored tunnels under the river Thames to serve a newly constructed underground station in Woolwich Town Centre.
Commissioning Authority: Docklands Light Railway
Principal Designer: Halcrow Group
Principal Architect: Weston Williamson
Main Contractor: Morgan Est / Colas Rail JV
- A highly successful PFI project completed ahead of programme and well below budget.
- A technically complex twin tunnel bore beneath the Thames and the challenging interface with existing rail lines and station made this a very difficult project to deliver successfully.
- The fully integrated team benefitted greatly from working together on previous projects.
- Strong community interface resulted in public satisfaction with the outturn.